Concrete Yard

How many cubic yards of concrete do you need for your pour?

Enter the length, width, and thickness of your concrete pour and get the exact cubic yards you need to order — including a waste factor so you do not come up short on pour day.

Updated July 2026 · How this works

Example calculation — edit any field to use your own numbers

Worth knowing
How It Works
The formula, explained simply

Picture filling a swimming pool with a garden hose — you calculate the pool volume first, then add extra for the hose you cannot drain and the water that splashes out during filling. Concrete works the same way. You start with the geometric volume of your pour, then build in a buffer for the physical realities of the job site.

The core calculation converts all three dimensions — length, width, and thickness — into the same unit (feet), multiplies them together to get cubic feet, and divides by 27 to convert to cubic yards, which is how ready-mix concrete is priced and delivered. For a circular pour like a column pier, the tool uses the area of a circle (pi times radius squared) instead of a simple rectangle, then applies the same thickness and conversion math.

The waste factor is applied as a straight multiplier on top of the net volume. At 10%, you are telling the tool that for every 10 yards you need, order 11. That extra yard covers the concrete left in the pump truck lines, the slight over-pour at form edges that gets struck off, and any soft spots in the subgrade that consume more material than the nominal depth. The rounded order quantity bumps the total up to the nearest 0.25 yard, which is the smallest increment most ready-mix plants will book.

When To Use This
Right tool, right situation

Use this tool whenever you need to call a ready-mix concrete plant with a specific order quantity, or when you are estimating material cost before bidding or budgeting a project. It is appropriate for slabs, driveways, sidewalks, garage floors, footings, pads, and any other rectangular or circular pour where thickness is uniform. It handles both residential DIY pours and contractor-scale commercial slabs.

This tool is not appropriate for tapered sections, haunched beams, stepped footings, or any pour where thickness changes along the length. Break those shapes into segments of uniform thickness, calculate each with this tool, and sum the results. It is also not a substitute for a structural engineer's specification on pours deeper than 12 inches, any pour in contact with post-tensioning cables, or slabs designed to carry vehicular loads heavier than standard passenger cars.

Do not rely on this tool's bag estimate as a cost comparison for large pours. Beyond about 1 cubic yard, ready-mix is almost always cheaper per cubic foot when labor and mixing time are factored in. The bag count is shown so you can make a quick go-or-no-go decision on whether to even call the plant, not as a detailed cost model.

Common Mistakes
Why results sometimes look wrong

Forgetting to convert thickness to the same unit as the other dimensions is the most common error in manual calculations. If you enter 4 inches as 4 in a formula that expects feet, you get a volume 3 times smaller than reality — a 10 by 10 slab reads as 0.41 yards instead of 1.23 yards. The builder orders one truck, the truck arrives nearly empty, and the pour cannot be completed. This tool handles the conversion automatically, but if you ever check the math by hand, divide inches by 12 before multiplying.

Using the gross dimensions instead of the inside form dimensions inflates the area. The concrete fills the space inside your forms, not including the form boards themselves. A 2x4 form board on each side of a 10-foot slab reduces the actual pour width by 3 inches, which matters on small pours and can add up on large footings with multiple offsets.

Skipping the waste factor entirely because the math works out clean is a mistake that causes short pours. Ready-mix drivers cannot add water at the site to stretch volume, and calling for a second truck mid-pour means a cold joint — a structural weak point where new concrete bonds poorly to partially-set material. The 10% default exists because contractors who skip it consistently run short; the ones who always use it occasionally have a small amount left over, which is a much less serious problem.

The Math
Worked examples and deeper derivation

The formula chain is: area (ft²) × thickness (ft) ÷ 27 = net cubic yards. Thickness in inches gets divided by 12 first — 4 inches becomes 0.333 feet. For metric inputs, length and width in meters are multiplied by 3.28084 to convert to feet, and thickness in centimeters is divided by 30.48 to reach feet. This keeps everything in the same unit system before the cubic yard conversion.

Waste is applied as: total yards = net yards × (1 + waste% ÷ 100). A 10% waste factor is a multiplier of 1.10, not an addition of 0.10. The rounded order quantity uses Math.ceil(total × 4) ÷ 4 — multiplying by 4 converts yards to quarter-yards, ceiling rounds up to the next integer, and dividing by 4 returns to yards. This guarantees you never order less than you need.

The bag estimate divides the net cubic feet by 0.45, which is the yield of a 60 lb bag. This is a net volume figure — no waste factor — because when you mix bags yourself you pour exactly what you mix with no residual left in a truck. A 60 lb bag at 0.45 ft³ means you need 60 bags per cubic yard, and the ceiling function ensures you always buy whole bags.

Two-car garage floor — typical residential pour
20 ft long, 22 ft wide, 5-inch thick slab, 10% waste, rectangular
Net volume is 8.15 cubic yards; with 10% waste you order 8.96 yards, rounded up to 9.0 yards. That is the most common residential pour and fits comfortably in one ready-mix truck. Ordering 9 yards instead of the exact 8.15 means you will not be scrambling to finish the pour with short material, and any leftover can fill post holes.
Paper-thin decorative overlay — edge case pour
15 ft long, 10 ft wide, 1.5-inch thick topping slab, 15% waste, rectangular
Net volume is only 0.69 cubic yards — well under the minimum delivery charge most ready-mix plants enforce (typically 1 cubic yard). The tool flags this range, signaling that a hand-mixed or pre-bagged approach is more practical and cheaper. At 0.45 cubic feet per 60 lb bag you would need about 45 bags, costing roughly the same as a short-load fee.
Structural engineer specifying a large mat foundation
50 ft long, 40 ft wide, 18-inch thick mat, 10% waste, rectangular
Net volume is 111.1 cubic yards; with waste the order is 122.2 yards, rounded to 122.25. At roughly 10 yards per truck that is 13 trucks. The tool correctly surfaces the multiple-truck warning. A professional would use this number as the basis for a concrete plant booking and a pump truck schedule, verifying that the plant can supply the full volume within the slump-life window of the specified mix.
Expert Unlock
The thing most explanations skip

The 10% waste factor is an industry convention, not a formula — it originates from pour crew experience, not from material science. On a perfectly formed, machine-graded slab with pump delivery, actual waste can be under 5%. On a hand-poured footing with variable-depth soil and wheelbarrow delivery, it can exceed 15%. The factor the tool applies is conservative by design; a contractor running tight margins will dial it down on clean pours and up on rough ones.

Ready-mix plants measure in whole tenths of a yard on the ticket, but the minimum chargeable increment varies by plant — some charge in 0.5-yard steps, others in 0.25-yard steps. Calling the plant before finalizing your order quantity is worth the two-minute conversation: a plant quoting 0.5-yard minimums makes the rounding step irrelevant for small pours and can change your decision between bag mix and truck delivery.

Why does my concrete order always end up higher than the raw volume?

How many cubic yards of concrete do I need for a 10 by 10 foot slab at 4 inches?
A 10 by 10 foot slab at 4 inches thick needs 1.23 cubic yards of net volume. With a standard 10% waste factor you should order 1.36 cubic yards, rounded up to 1.5 yards for a ready-mix delivery. Many suppliers have a 1 cubic yard minimum, so this size sits right at the practical threshold for truck delivery versus bag mixing.
What waste factor should I use when ordering concrete for a slab?
10% is the standard waste factor for a flat, rectangular slab with a well-prepared subgrade. Use 12 to 15% for irregular shapes, sloped sites, or footings with variable depth. Never use 0% — even a perfect rectangular pour loses material to subgrade irregularity, form blowout protection, and pump hose residue.
How many 60 lb bags of concrete equal one cubic yard?
A standard 60 lb bag of dry concrete mix yields about 0.45 cubic feet when mixed. One cubic yard equals 27 cubic feet, so you need roughly 60 bags per cubic yard. At typical retail pricing, bag mixing costs more than ready-mix for any pour over about 1 cubic yard, which is why the tool shows the bag count as a comparison reference.

Need something this doesn't cover?

Suggest a tool — we'll build it →