Online Concrete Calculator

How much concrete do you need for your slab or footing?

Enter your slab, footing, or column dimensions and get the exact volume of concrete you need — in cubic yards, cubic feet, and 60 lb or 80 lb bag counts. Includes a standard waste allowance so you never come up short on pour day.

Updated July 2026 · How this works

Example calculation — edit any field to use your own numbers

Worth knowing
How It Works
The formula, explained simply

Picture filling a perfectly rectangular box with water. The amount of water you need is simply the three dimensions multiplied together. Concrete volume works exactly the same way — length times width times thickness gives you the raw space that needs to be filled. The only complication is that concrete comes measured in cubic yards, while most people think in feet and inches, which forces a unit conversion that trips up a lot of DIYers.

The formula adds one practical layer on top of pure geometry: a waste allowance. No real pour goes into the forms with zero loss. Concrete spills off trowels, settles into low spots in the subgrade that your tape measure did not capture, and partially fills honeycombs in the form faces. A standard 10 percent waste buffer means you order a volume 10 percent larger than the theoretical box — so if your slab needs 1.48 yd³ yd³ of concrete, you actually order 1.63 yd³ yd³.

Bag counts are derived from the manufacturer-rated yield of premix bags. A 60 lb bag is rated at 0.45 cubic feet of mixed concrete; an 80 lb bag at 0.6 cubic feet. The tool divides your total adjusted volume by each yield and rounds up to the nearest whole bag — you cannot buy a fraction of a bag, and coming up one short on pour day is a serious problem. Always round up.

When To Use This
Right tool, right situation

Use this calculator any time you are pouring a uniform slab, pad, footing, or column and need to know how much material to buy or order before the truck arrives. It is most reliable for simple rectangular geometry: driveways, sidewalks, garage floors, patio slabs, and post footings. The result is an estimate, not a guarantee — on-site conditions always introduce variation.

This tool is less appropriate for complex pours with tapers, multiple lifts, or varying cross-sections. A stepped footing, for example, needs to be broken into individual rectangular sections and summed. Large commercial pours with engineered drawings should always be quantity-taken from those drawings, with this calculator used only as a rough sanity check.

If your result exceeds roughly 10 cubic yards, step away from the bags-of-concrete aisle and call a batch plant. Ready-mix is priced by the yard and the per-unit cost drops significantly at volume, while the labor cost of mixing and placing hundreds of bags by hand becomes prohibitive. The boundary warning in this tool flags that threshold automatically.

Common Mistakes
Why results sometimes look wrong

Measuring thickness in feet instead of inches. This is the most frequent input error and it produces a result roughly twelve times too large. If the tool shows a volume that seems unreasonably high, check whether you entered thickness as 4 inches or accidentally typed 4 feet. A 4-foot slab is a dam, not a patio.

Skipping the waste allowance and assuming zero loss. Experienced finishers know that concrete volume is never exact in practice. The subgrade compacts unevenly, forms bow under pressure, and some material always stays in the mixer drum. Ordering exactly the calculated net volume leaves no margin — the most likely outcome is a short pour that either leaves a gap in the slab or forces a cold joint repair that costs more than a few extra bags would have.

Using bag count as a proxy for ready-mix quantity. Ready-mix trucks deliver in cubic yards, not bags. The bag count shown here is for purchasing premix at a hardware store. If you are getting a truck delivery, give the batch plant your cubic-yard number — which is 1.63 yd³ yd³ for the example project — not the bag count. Mixing up these numbers can result in a truck delivering the wrong load.

The Math
Worked examples and deeper derivation

The core geometry for a rectangular slab converts all dimensions to feet first. Length and width are already in feet; thickness in inches is divided by 12 (the number of inches per foot) to get feet. Volume in cubic feet is then length (ft) × width (ft) × thickness (ft). For the example slab of 12 ft × 10 ft × 4 in, the net volume works out to 1.48 yd³ yd³ after the cubic-yard conversion.

Converting cubic feet to cubic yards requires dividing by 27 — the number of cubic feet in one cubic yard. This single conversion is where most hand-calculation errors occur: people divide by 9 (the square-foot conversion) instead of 27 (the cubic conversion). The adjusted volume with waste is: net volume × (1 + waste percent ÷ 100). For the example with 10 percent waste, that gives 1.63 yd³ yd³.

Circular columns use the cylinder formula: volume = π × radius² × height. The radius is half the diameter. All dimensions are converted to a common base unit in metres first, then the result is converted back to cubic feet and cubic yards for display. Bag counts are always computed on the waste-adjusted volume and always rounded up: bags needed = ceiling(total cubic feet ÷ yield per bag). For 60 lb bags yielding 0.45 ft³ each, the example slab requires 98 bags bags.

Backyard patio slab — standard residential pour
12 ft long, 10 ft wide, 4 inch thick slab with 10 percent waste allowance
The net slab volume is 1.48 yd³ yd³. Adding the 10 percent waste allowance brings the order quantity to 1.63 yd³ yd³ (44 ft³ ft³). You would need 98 bags sixty-pound bags or 74 bags eighty-pound bags. At this volume, bagged concrete is practical but you are near the threshold where calling a ready-mix supplier starts saving money.
Deck support columns — circular sonotubes
1.5 ft diameter, 3 ft tall circular column, 10 percent waste allowance
The column volume with waste works out to 0.22 yd³ yd³ (5.83 ft³ ft³). For deck footings you typically pour several columns on the same day — multiply this figure by the number of columns before heading to the hardware store. You need 13 bags sixty-pound bags or 10 bags eighty-pound bags per column.
Large commercial floor slab — metric project
3.6 m long, 3.0 m wide, 10 cm thick slab with 10 percent waste, metric units
Working in metric, the tool converts dimensions to a base volume and then adds the waste allowance, giving 1.55 yd³ yd³ (41.95 ft³ ft³) as the total order quantity. Even on metric projects, ready-mix is quoted in cubic metres, so use the cubic-feet figure to cross-check your batch plant quote. At this volume you would need 94 bags sixty-pound bags or 70 bags eighty-pound bags if bagging manually.
Expert Unlock
The thing most explanations skip

The bag-yield figures used here (0.45 ft³ for 60 lb, 0.6 ft³ for 80 lb) are manufacturer-rated yields at the water-to-cement ratio specified on the bag. In practice, contractors often add slightly more water for workability, which reduces compressive strength and increases actual yield marginally — meaning real-world bag counts can run 2 to 5 percent higher than this tool predicts. For structural applications, use the manufacturer spec and accept the conservative count.

The 10 percent waste default is a rule-of-thumb for flat, well-prepared subgrades. Geotechnical variation, form deflection under hydraulic pressure, and pump or chute losses on larger pours can push actual waste to 15 percent or more. Experienced site supervisors calibrate their waste factor to the specific subgrade condition and form system, not a fixed percentage — treat this tool as the starting point, not the final answer.

What do these concrete volume numbers actually mean for my project?

How many 60 lb bags of concrete do I need for a 10x10 slab?
For a 10 ft by 10 ft slab at 4 inches thick with a 10 percent waste allowance, the calculation gives 98 bags sixty-pound bags based on the example dimensions in this tool. The exact count depends on your thickness — every extra half-inch adds roughly 4 to 5 bags on a slab this size, so measure your forms carefully before buying.
When should I order ready-mix concrete instead of buying bags?
Once your pour exceeds about 1 cubic yard, ready-mix becomes competitive on price and saves significant labor mixing bags by hand. Beyond roughly 10 cubic yards, bags are almost never the right call — the per-yard cost of ready-mix drops sharply and the mixing time for that many bags is not practical for a single pour day.
Does the waste allowance really matter, or can I skip it?
Skipping the waste allowance is one of the most common and expensive mistakes on a pour day. Concrete cannot be added to a partially cured slab without creating a cold joint that weakens the structure. Even on a flat, well-prepared subgrade, experienced contractors rarely pour with less than 8 percent waste built in — rough or rocky ground warrants 15 percent or more.

Need something this doesn't cover?

Suggest a tool — we'll build it →